Logan Hospital

Building 1

Day Procedure Unit (SD, GCS, DD & CD through to handover all disciplines)

  • The Day Procedure Unit had to be built within the existing building that contained the Emergency Department, this meant there were challenges as where practical the existing major infrastructure was to remain such as AHUs, electrical switchboards, sewer connections et
  • The key outcome is that the client is satisfied that they are receiving a design that provides a design solution that is compliant with the relevant standards, codes and requirements of the contract, a design that meets their requirements, value for money, evidence based design process had been undertaken, fit for purpose, and that adequate due diligence has occurred throughout the design process
  • We believe we provided valuable support for the client, and based on our observations and recommendations assisted in ensuring a better outcome for the project. During the design process we offered alternative design solutions architecturally that allowed the main switch board to be relocated that increased the size of the one of the operating theatres and the flows of the remaining areas
  • Reviewed all the design documentation during each of the design stages, including the GCS, for compliance with Australian standards, other regulation and guidelines as included in the contract and the signed off base documents. The documents included drawings, reports for each of the design stages, specifications, supporting design information etc.
  • As the independent clients representative we attended all meetings, design, user group meetings, client meetings, managing contractor meetings etc.
  • Provided reports at each design stage with our observations of any non-compliances with the standards, codes, agreed scope etc as per the contract, provided alternative design solutions and or recommendations where we thought it would benefit the client.
  • Following the issue of each report there would be a number of meetings with the design team and or the managing contractor depending on the design stage where the observations were discussed and depending on the discussions an outcome would be agreed.

Early Pre-Operative Services (EPOS) and Early Pregnancy Assessment Unit (EPAU) (CD documents all disciplines)

  • Early in the design process this area was to be the 23hr Ward before the use was changed, it is located adjacent to the Day Procedure Unit and had to be built within the existing building that contained the Emergency Department, this meant there were challenges as where practical the existing major infrastructure was to remain such as AHUs, electrical switchboards, sewer connections etc.
  • This project was designed using a new team separate to the Emergency Department Expansion and DPU works, our role comprised of an initial briefing where we provided some background on the building and some lessons learnt from our previous involvement, we reviewed the design teams design documentation at the CD stage and provided a report with our observations. We had a follow up meeting where we discussed our observations and through this process the proposed changes were agreed for inclusion in the design documents.
  • We had a special interest in this project as we completed the mechanical design which was incorporated in part in the design documents. It should be noted that not all of our design recommendations were adopted during construction.
  • The key outcome is that the client is satisfied that they are receiving a design that provides a design solution that is compliant with the relevant standards, codes and requirements of the contract, a design that meets their requirements, value for money, evidence based design process had been undertaken, fit for purpose, and that adequate due diligence has occurred throughout the design process.
  • We believe we provided valuable support for the client, and based on our observations and recommendations assisted in ensuring a better outcome for the project.

Building 3

Emergency Department Expansion (SD, DD, GCS & CD through to handover all disciplines)

  • The Emergency Department Expansion was a new four storey building, providing a range of health services in addition to the emergency department. The lower level included parking, storage, engineering services such as main switch room, generator, chillers, UPS, comms room, fire services etc. Levels two and three were clinical floors with level two the main point of access. Level four was all plantroom, where all the air handling systems were located including miscellaneous services with the cooling towers located on the roof on Level four.  This building was designed to be extended in the future to eight levels.
  • The key outcome is that the client is satisfied that they are receiving a design that provides a design solution that is compliant with the relevant standards, codes and requirements of the contract, a design that meets their requirements, value for money, evidence based design process had been undertaken, fit for purpose, and that adequate due diligence has occurred throughout the design process.
  • We believe we provided valuable support for the client, and based on our observations, recommendations additional reports assisted in ensuring a better outcome for the project. One example was we noticed the lift car sizing for the purpose specified was undersized, this meant that the lift design was reviewed and all the lift cars were increased in size to the maximum.
  • Reviewed all the design documentation during each of the design stages, including the GCS, for compliance with Australian standards, other regulation and guidelines as included in the contract and the signed off base documents. The documents included drawings, reports for each of the design stages, specifications, supporting design information etc.
  • As the independent clients representative we attended all meetings, design, user group meetings, client meetings, managing contractor meetings etc.
  • Provided reports at each design stage with our observations of any non-compliances with the standards, codes, agreed scope etc as per the contract, provided alternative design solutions and or recommendations where we thought it would benefit the client.
  • Following the issue of each report there would be a number of meetings with the design team and or the managing contractor depending on the design stage where the observations were discussed and depending on the discussions an outcome would be agreed.
Logan Hospital

Building 1

Day Procedure Unit (all disciplines) Principles representative responsible for undertaking the end of defects liability inspections for all building services engineering

  • Twelve months after the construction of the Day Procedure Unit we undertook the end of defects liability inspections.
  • In our reporting we identify all defects in a spreadsheet that is a living document that shows each stage of the discussion phase with the client and the design team/managing contractor. Photographs are provided showing the defects identified or multiple defects depending on the situation.
  • The inspections included checking that all the defects from our end of construction inspections had been rectified and any new defects or non-compliances that had occurred during the past twelve months.
  • The areas inspected included:
    • Within the plantrooms
    • Within the ceiling/roof spaces
    • The occupied floor
  • The services included:
    • Mechanical services, checking the air conditioning, ductwork distribution, integrity of insulation, air handling checks, exhaust systems, chilled water, condensate waste, fire systems, MSSBs, segregation etc
    • Medical gases, checking pipework, outlets, supports, segregation from other services etc
    • BMS, checking that BMS was completed, any control issues etc
    • Electrical services, checking medical service panels, electrical switch boards, electrical cabling, fire services cabling, lighting, segregation etc
    • Comms, checking comms rooms, cable installations, segregation etc
    • Fire systems, checking sprinkler pump room, FIPs, fire cabling installation, segregation etc
    • Hydraulics, checking pipework, extent of insulation on hot water, valves, segregation etc
    • Fire penetrations, checking that all penetrations previously identified and installed within the twelve months had been sealed, adequately certified, photographed and recorded in the fire penetration register and recorded on the As Installed drawings.
    • Check that the building envelope insulation had been sealed, this is critical in reducing the extent of infiltration. The roof space based on our observations are a concern.
  • We found many instances where the defects previously identified as documentation shortfalls or non-compliances had not been rectified over the previous twelve months.

Building 3

Emergency Department Expansion (all disciplines) Principles representative responsible for undertaking the end of defects liability inspections for all building services engineering.

  • Twelve months after the construction of the Emergency Department Expansion we undertook the end of defects liability inspections over a number of stages which reflected the staged practical completion of the project.
  • In our reporting we identify all defects in a spreadsheet that is a living document that shows each stage of the discussion phase with the client and the design team/managing contractor. Photographs are provided showing the defects identified or multiple defects depending on the situation.
  • The inspections included checking that all the defects from our end of construction inspections had been rectified and any new defects or non-compliances that had occurred during the past twelve months.
  • The areas inspected included:
    • Within the plantrooms
    • Within the ceiling/roof spaces
    • The occupied floor
  • The services included:
    • Mechanical services, checking the air conditioning, ductwork distribution, integrity of insulation, air handling checks, exhaust systems, chilled water, condensate waste, fire systems, MSSBs, segregation etc
    • Medical gases, checking pipework, outlets, supports, segregation from other services etc
    • BMS, checking that BMS was completed, any control issues etc
    • Electrical services, checking medical service panels, electrical switch boards, electrical cabling, fire services cabling, lighting, segregation etc
    • Comms, checking comms rooms, cable installations, segregation etc
    • Fire systems, checking sprinkler pump room, FIPs, fire cabling installation, segregation etc
    • Hydraulics, checking pipework, extent of insulation on hot water, valves, segregation etc
    • Fire penetrations, checking that all penetrations previously identified and installed within the twelve months had been sealed, adequately certified, photographed and recorded in the fire penetration register and recorded on the As Installed drawings.
  • We found many instances where the defects previously identified as documentation shortfalls or non-compliances had not been rectified over the previous twelve months.
  • Check that the building envelope insulation had been sealed, this is critical in reducing the extent of infiltration. The roof space based on our observations are a concern.
Logan Hospital Building Services

Building 1

  • Investigate and provide detailed reports in relation the upgrade of all mechanical systems associated with the eight Operating Theatres, CSSD & two Endoscopy Procedure Rooms in Building 2
  • Review of the Pharmacy and Pathology Department air conditioning systems.
  • Investigate Main Switch Board MSB4 and provide recommendations and strategy for shutting down to enable upgrade modifications.
  • Investigate the chilled water system for the addition of future air handling systems.

Building 2

  • Investigate the Potable Water Quality Issues for the cause of the biofilm contamination and recommendations to rectify and update of procedures to avoid issues in the future.
  • Investigate the water supply to the endoscopy unit and provide recommendations to rectify the problems.
  • Investigate the types of instantaneous hot water units located in staff rooms and tea rooms that biofilm contamination can be removed without replacing the units, provided recommendations on the types of instantaneous hot water units that can dismantled to enable deep cleaning without replacing the unit.

Building 3

  • Investigate and report the requirements for providing Outside Air Pre-Conditioning AHUs to the level 4 plantroom
Building Services Logan Hospital

Building 1

  • Principles Representative (Clerk of Works) for Building Engineering Services during Construction and Defects Liability for the Day Procedure Unit (all disciplines)

Building 3

  • Principles Representative (Clerk of Works) for Building Engineering Services during Construction and Defects Liability for the Emergency Department Expansion (all disciplines)

Building 1

  • Pathology & Pharmacy air conditioning rectification work
  • Mechanical Services Associated with the DPU Enabling Works
Hospital Building Services Engineer

Building 1

  • Early Pre-Operative Services (EPOS) and Early Pregnancy Assessment Unit (EPAU), Design and documentation of the mechanical services, air conditioning and ventilation etc
  • Design for the replacement of seven AHU Systems
  • Pathology & Pharmacy, Design and documentation of the air conditioning rectification works.
  • Day Procedure Unit Enabling Works during the construction of the Early Pre-Operative Services (EPOS) and Early Pregnancy Assessment Unit (EPAU), Design and documentation of the mechanical services, air conditioning and ventilation etc.